Présenté par: MAILELE Djibril Amadou, Directeur Production & Transport - NIGELEC
PLAN DE LA PRESENTATION 1. CONTEXTE 2. AVENNEMENT DE LA PANNE 3. CONSEQUENCES DE LA PANNE 4. SOLUTION DU DEPANNAGE DEFINITIF 5. SOLUTION DU DEPANNAGE PROVISOIRE 6. MISE EN ŒUVRE DU DEPANNAGE PROVISOIRE 7. ENSEIGNEMENTS TECHNIQUES & CONCLUSION
1. CONTEXTE LA LIGNE KAINJI BIRNIN KEBBI EST LA SEULE LIAISON 330KV ALIMENTANT LA ZONE NORD OUEST DU NIGERIA À PARTIR DU BARRAGE DE KAINJI SUR UNE LONGUEUR DE 310KM JUSQU À BIRNIN KEBBI. LE POSTE DE BIRNIN KEBBI COMPREND 2 TRAVÉES TRANSFORMATEUR 330/132KV - 90MVA QUI ALIMENTENT L ETAT DE SOKOTO, L ETAT DE KEBBI ET LA ZONE DU FLEUVE AU NIGER. LA ZONE DU FLEUVE AU NIGER COMPREND 2 RÉGIONS ET NIAMEY LA CAPITALE. LA POINTE ENREGISTRÉE LE 6 MAI 2013 POUR CETTE ZONE INTERCONNECTÉE A ATTEINT 103MW, AVEC UNE IMPORTATION TOTALE DE 60MW SUR LA LIGNE D INTERCONNEXION 132KV ET UNE PRODUCTION LOCALE COMPLÉMENTAIRE ASSURÉE PAR UN PARC D UNE PUISSANCE DISPONIBLE DE 56MW. LA DEMANDE EN ÉNERGIE ÉLECTRIQUE EST MAXIMALE PENDANT LA PÉRIODE CHAUDE À CAUSE ESSENTIELLEMENT DES BESOINS EN CLIMATISATION.
2. AVENNEMENT DE LA PANNE La panne ayant entrainé le déclenchement de la ligne Kainji Birnin Kebbi est intervenue dans la nuit du 24 au 25 mai 2013. Trois (03) pylônes d alignement 330kV se sont effondrés suite à des précipitations extrêmement violentes (Vent, orage, grêle). Pylônes 618 619 620
2.1. PYLÔNE 618 / RUINE
2.2. PYLÔNE 619 / DÉCAPITÉ
2.3. PYLÔNE 620 / RUINE
3.1 CONSEQUENCES DE LA PANNE AU NIGERIA INTERRUPTION DU SERVICE PUBLIC D ELECTRICITE ETAT DE SOKOTO (TOTALEMENT) ETAT DE KEBBI (TOTALEMENT) ETAT DE ZANFARA (PARTIELLEMENT)
3.2. CONSEQUENCES DE LA PANNE AU NIGER PERTE DE LA LIGNE D INTERCONNEXION (-52MW à Niamey, -5MW à Dosso et -3MW à Gaya) ACCROISSEMENT DE PRODUCTION D ENERGIE ELECTRIQUE SUR BASE THERMIQUE (Passage de 4.181 GWH/Semaine à 8.115 GWh/ Semaine, soit +3.933GWH/Semaine) DELESTAGE DE CONSOMMATION (jusqu à 3.413 GWH/ semaine d énergie non livrée) L INCIDENCE DE L INDISPONIBILITE DE LA LIGNE D INTERCONNEXION POUR NIGELEC A ETE ESTIME A UNE PERTE NETTE DE 452 MILLIONS FCFA PAR SEMAINE
4. SOLUTION DU DEPANNAGE DEFINITIF REMPLACEMENT DES PYLONES RUINES ET REPARATION DU CONDUCTEUR AVANTAGES: REMISE EN ETAT DE LA LIGNE A 100% INCONVENIENTS: TEMPS DE MISE EN ŒUVRE LONG SI LES FONDATION SONT A REPRENDRE CONTRAINTE DE TROUVER LES PYLONES QUI MONTENT SUR LES FONDATIONS EXISTANTES LE CONTRAT DE REMISE EN ETAT DE LA LIGNE A ÉTÉ SIGNE AVEC UN LE CONTRAT DE REMISE EN ETAT DE LA LIGNE A ÉTÉ SIGNE AVEC UN ENTREPRENEUR DEPUIS LE 29 MAI 2013 POUR UNE DUREE DE 30 JOURS. A DATE SEULES LES FONDATIONS ONT ÉTÉ ACHEVEES, LE PYLONES AYANT FAIT L OBJET D UNE NOUVELLE COMMANDE POUR NON CONFORMITE DES CORNIERES INITIALEMENT PROPOSEES.
5. SOLUTION DU DEPANNAGE PROVISOIRE CONSTRUCTION D UNE LIGNE DE DEVIATION DE 1970M SUR SUPPORTS EN BETON ARME. PBA DE 12M ET CONDUCTEUR 117MM² ALMELEC MONTÉ SUR ARMEMENTS EN NAPPE HORIZONTALE AVEC DES ISOLATEURS COMPOSITES 330KV EN TRIANGLE. MISE EN ŒUVRE CONJOINTE PAR LES DEUX SOCIÉTÉS EN ASSOCIANT MOYENS HUMAINS, MATÉRIELS ET FINANCIERS SOLUTION CONVENUE CONJOINTEMENT ENTRE PHCN/TCN ET NIGELEC le 02 juin 2013. PHCN/TCN: ARRÊT DES DEUX EXTRÉMITÉS DE LA LIGNE 330KV ET FOURNITURE DES HERSES ET ISOLATEURS COMPOSITES NIGELEC: FOURNITURE DES SUPPORTS EN BÉTON ARMÉ, DU CONDUCTEUR ET DES PINCES
5. SOLUTION DU DEPANNAGE PROVISOIRE AVANTAGES: MISE EN ŒUVRE RAPIDE PERMETTRE UNE MEILLEURE ORGANISATION DU CHANTIER DE DEPANNAGE DEFINITIF INCONVENIENTS: REMISE EN ETAT DE LA LIGNE A FAIBLE CAPACITE RISQUES D EXPLOITATION LIES A LA SOLUTION IMPACTS ENVIRONNEMENTAUX / DIFFICULTE DE RETRAIT DE LA LIGNE APRES LE DEPANNAGE DEFINITIF
6.1. MOBILISTATION ET DEMARRAGE TRAVAUX PHCN / TCN: MOBILISATION DES EQUIPES, VEHICULES ET ENGINS DES LE 8 JUIN 2013 APPROVISIONNEMENT DU CHANTIER EN MATERIEL (HERSES ET POLYMERES) LE 11 JUIN 2013 NIGELEC: MOBILISATION DES EQUIPE, VEHICULES ET ENGINS DU 6 AU 8 JUIN 2013 APPROVISIONNEMENT DU CHANTIER EN MATERIEL AU 10 JUIN 2013 DEMARRAGE DES TRAVAUX AVEC LE PIQUETAGE LE 7 JUIN 2013.
6.1. PHOTOS
6.1. PHOTOS
6.2. REALISATION DES TRAVAUX PHCN / TCN: REALISATION DES ARRETS DES DEUX EXTREMITES DE LIGNE 330kV REALISATION DES BRETELLES DE RACCORDEMENT NIGELEC: IMPLANTATION SUPPORT / ARMEMENT / DEROULAGE ET TIRAGE CONDUCTEURS
6.2. PHOTOS
6.2. PHOTOS
6.2. PHOTOS
6.2. PHOTOS
6.3. RUINE DU QUATRIEME PYLONE N 621 LE 14 JUIN 2013 VERS 14 HEURES, ALORS QUE L EQUIPE DE TCN REALISAIT LES BRETELLES DE RACCORDEMENT SUR LE PYLONE 621, CE DERNIER S EFFONDRE AVEC DEUX LIGNARDS, BIEN HEUREUSEMENT SANS VICTIME. DISPOSITIONS PRISES: REUNION DE COORDINATION TCN / NIGELEC APPROVISIONNEMENT MATERIEL COMPLEMENTAIRE POUR REALISER UNE DEVIATION ADDITIONNELLE DE 400M (SOIT 2.37KM DE DEVIATION EN TOUT).
6.3. PHOTOS
6.4. POURSUITE ET FINALISATION DES TRAVAUX POURSUITE ET FINALISATION DES TRAVAUX : PHCN / TCN: REALISATION DES ANCRAGES SUR PYLONE N 622 RENFORCEMENT DES ANCRAGES SUR LE PYLONE N 617 NIGELEC: CONSTRUCTION DE LA DERIVATION ADDITIONNELLE DE 400M MISE SOUS TENSION DE LA LIGNE LE 18 JUIN 2013 AVEC UNE LIMITATION DE PUISSANCE DE 100MW LIEE A LA CAPACITE THERMIQUE DU CONDUCTEUR ALMELEC 117MM²
6.4. PHOTO
7.1. BILAN TECHNIQUE LES TRAVAUX ONT ÉTÉ REALISES DANS UN DELAI APPRECIABLE. ET LA FOURNITURE D ELECTRICITE A ÉTÉ RETABLIE DANS LES ZONES AFFECTEES, CEPENDANT AVEC UNE LIMITATION TECHNIQUE DE PUISSANCE A 100MW. LES TRAVAUX ONT NECESSITE LA MOBILISATION DES MOYENS SUIVANTS: PHCN / TCN: 35 AGENTS 02 GRUES + 04 VEHICULES LAND-ROVER NIGELEC: 22 AGENTS ET 30 MANAOEUVRES ET OUVRIERS CONTRACTUELS 04 GRUES + 5 PICKUP TOYOTA + 1 NACELLE 03 GROUPES ELECTROGENES
7.1. BILAN TECHNIQUE LE MATERIEL SUIVANT A ÉTÉ UTILISE SUR LE CHANTIER PHCN / TCN: 234 polymères 330kV AVEC ACCESSOIRES LES CORNIERES DE TOUT TYPE NIGELEC: 129 POTEAUX BETON ARMES DE 12M ET D EFFORTS VARIANT ENTRE 1250daN ET 500daN 7500M DE CONDUCTEUR ALMELEC 117MM² DIVERS ACCESSOIRES DE D ANCRAGE ET D ALIGNEMENT
7.2. RETOUR D EXPERIENCE EN EXPLOITATION L EXPLOITATION DE L A DERIVATION PROVISOIRE A REVELE QUELQUES PROBLEMES LIES AUX VIBRATIONS DE LA LIGNE DEPUIS SA MISE SOUS TENSION: - PERTE D ECROUS DE MANILLES ET DE GOUPILLES AYANT OCCASIONNE DEUX COUPURES DE LA LIGNE POUR MAINTENANCE LES 20 JUILLET ET LE 12 SEPTEMBRE 2013. - LA RUPTURE D UN CABLE D ANCRAGE DES PYLONES EXTREMES. NOTER QUE CES VIBRATIONS SONT TRES IMPORTANTES SURTOUT EN TEMPS DE NOTER QUE CES VIBRATIONS SONT TRES IMPORTANTES SURTOUT EN TEMPS DE PLUIE COMME L INDIQUE LES VIDEO SUIVANTES:
7.2. PHOTOS
7.2. VIDEO 1
7.2. VIDEO 2
7.3. CONCLUSION EN CONCLUSION IL FAUDRA NOTER QUE MALGRE SES INSUFISANCES TECHNIQUES, LA SOLUTION DE DEVIATION PROVISOIRE DE LA LIGNE A ÉTÉ D UNE UTILITE CERTAINE ET A PERMIS DE REALISER DES ECONOMIES SUBSTANCIELLES PARTICULIEREMENT POUR NIGELEC. IL FAUDA CEPENDANT NOTER QUE LA MISE EN ŒUVRE DE CETTE IL FAUDA CEPENDANT NOTER QUE LA MISE EN ŒUVRE DE CETTE SOLUTION A PARADOXALEMENT BEAUCOUP RETARDE LA MISE EN ŒUVRE DE LA SOLUTION DEFINITIVE POUR LAQUELLE LES PYLONES NE SONT TOUJOURS PAS APPROVISIONNES SUR LE CHANTIER.